Violet Street Bridge replacement
The Violet Street Bridge replacement will see the construction of a new bridge over Narrabri Creek.
The project will include the removal of the existing bridge, which will be replaced with a steel reinforced concrete structure and new road approaches.
The new bridge will feature unrestricted load capacity, dual traffic lanes, shared pathways along both sides and new overhead street lighting.
The $7 million project has been made possible with the contribution of $5 million through the Infrastructure Betterment Program jointly funded by the Australian and NSW Governments under the Disaster Recovery Funding Arrangements.
The Australian Government’s Roads to Recovery Program contributed the remaining $2 million for the project.
The new Violet Street Bridge will:
- Be a safer, wider bridge that will cater for all vehicles as well as pedestrians and cyclists.
- Allow unrestricted heavy vehicle access.
- Provide a shared pathway on both sides of the bridge for pedestrians and cyclists, connecting to the existing shared pathway network.
- Decrease time to remove barriers during flood events, reducing the initial closure time of the bridge and lessening disruption for residents and road users during flood events.
A detour remains in place throughout the duration of the works. The detour route is in place along Selina Street, Newell Highway and Tibbereena Street: 
Works are expected to be completed by mid November (depending on weather and other factors).
The Violet Street Bridge replacement will see the construction of a new bridge over Narrabri Creek.
The project will include the removal of the existing bridge, which will be replaced with a steel reinforced concrete structure and new road approaches.
The new bridge will feature unrestricted load capacity, dual traffic lanes, shared pathways along both sides and new overhead street lighting.
The $7 million project has been made possible with the contribution of $5 million through the Infrastructure Betterment Program jointly funded by the Australian and NSW Governments under the Disaster Recovery Funding Arrangements.
The Australian Government’s Roads to Recovery Program contributed the remaining $2 million for the project.
The new Violet Street Bridge will:
- Be a safer, wider bridge that will cater for all vehicles as well as pedestrians and cyclists.
- Allow unrestricted heavy vehicle access.
- Provide a shared pathway on both sides of the bridge for pedestrians and cyclists, connecting to the existing shared pathway network.
- Decrease time to remove barriers during flood events, reducing the initial closure time of the bridge and lessening disruption for residents and road users during flood events.
A detour remains in place throughout the duration of the works. The detour route is in place along Selina Street, Newell Highway and Tibbereena Street: 
Works are expected to be completed by mid November (depending on weather and other factors).
-
Violet Street Bridge update - 27 July 2026
Share Violet Street Bridge update - 27 July 2026 on Facebook Share Violet Street Bridge update - 27 July 2026 on X (formerly Twitter) Share Violet Street Bridge update - 27 July 2026 on Linkedin Email Violet Street Bridge update - 27 July 2026 linkThe completion of the replacement Violet Street Bridge has been delayed until mid-November, due to difficult ground conditions encountered during piling, resulting in an adjustment to the overall project timeline.
The project is now programmed to be finished and open to traffic in mid-November 2026, subject to weather conditions.
Council is currently working with the project’s contractor on anticipated cost increases due to the adjusted program schedule. A report regarding these costs will be presented to Councillors at next month’s Ordinary Council Meeting.
Despite the program adjustment, works are continuing at a steady pace, with installation of the precast pile caps for Pier 3 and Pier 2 as well as construction of the abutment on the Tibbereena Street side. Steel fixing has also been completed for the abutment on the Selina Street side.
Upcoming works for the remainer of this month will focus on construction of the Pier 2 and Pier 3 blade walls.
Next month will involve the construction and installation of the precast pile cap for the Pier 1 pile group and the Pier 1 blade wall, along with demolition of existing bridge piers. Construction of the headwalls for each pier will also take place, as will construction of Abutment A.
September will see works move to the installation of bridge girders and construction of the bridge deck.
The completion of the replacement Violet Street Bridge has been delayed until mid-November, due to difficult ground conditions encountered during piling, resulting in an adjustment to the overall project timeline.
The project is now programmed to be finished and open to traffic in mid-November 2026, subject to weather conditions.
Council is currently working with the project’s contractor on anticipated cost increases due to the adjusted program schedule. A report regarding these costs will be presented to Councillors at next month’s Ordinary Council Meeting.
Despite the program adjustment, works are continuing at a steady pace, with installation of the precast pile caps for Pier 3 and Pier 2 as well as construction of the abutment on the Tibbereena Street side. Steel fixing has also been completed for the abutment on the Selina Street side.
Upcoming works for the remainer of this month will focus on construction of the Pier 2 and Pier 3 blade walls.
Next month will involve the construction and installation of the precast pile cap for the Pier 1 pile group and the Pier 1 blade wall, along with demolition of existing bridge piers. Construction of the headwalls for each pier will also take place, as will construction of Abutment A.
September will see works move to the installation of bridge girders and construction of the bridge deck.
-
Major milestone for Violet Street Bridge
Share Major milestone for Violet Street Bridge on Facebook Share Major milestone for Violet Street Bridge on X (formerly Twitter) Share Major milestone for Violet Street Bridge on Linkedin Email Major milestone for Violet Street Bridge linkThe replacement of Narrabri’s Violet Street Bridge has achieved a major milestone with completion of foundation piling works on the project.
The final pile was driven on 24 June for the bridge’s abutment on the Selina Street end of the bridge, marking the completion of these works.
The first concrete pour for the abutment at the Tibbereena Street end of the bridge has also been completed.
All pier piles are being cut down to the design level, while steelwork for pile caps for each pier is underway.
Focus will also move to demolition of the old bridge piers, which were used to support the temporary pile guide frames. These existing bridge piers are scheduled to be demolished in mid-July.
In addition to demolition of existing piers, the bridge’s next milestone will include the construction of the pile caps, blade piers and the abutment at the Selina Street end of the bridge.
This is expected to take approximately six weeks, after which construction of the headstocks and placement of the girders will take place – and another step closer to completion of new Violet Street Bridge.
The replacement of Narrabri’s Violet Street Bridge has achieved a major milestone with completion of foundation piling works on the project.
The final pile was driven on 24 June for the bridge’s abutment on the Selina Street end of the bridge, marking the completion of these works.
The first concrete pour for the abutment at the Tibbereena Street end of the bridge has also been completed.
All pier piles are being cut down to the design level, while steelwork for pile caps for each pier is underway.
Focus will also move to demolition of the old bridge piers, which were used to support the temporary pile guide frames. These existing bridge piers are scheduled to be demolished in mid-July.
In addition to demolition of existing piers, the bridge’s next milestone will include the construction of the pile caps, blade piers and the abutment at the Selina Street end of the bridge.
This is expected to take approximately six weeks, after which construction of the headstocks and placement of the girders will take place – and another step closer to completion of new Violet Street Bridge.
-
Violet Street Bridge update - 18 June 2026
Share Violet Street Bridge update - 18 June 2026 on Facebook Share Violet Street Bridge update - 18 June 2026 on X (formerly Twitter) Share Violet Street Bridge update - 18 June 2026 on Linkedin Email Violet Street Bridge update - 18 June 2026 link
Piling works are continuing on foundations for the new Violet Street Bridge, with Pier 1 completed on 17 June. Abutment A is scheduled to be completed by 26 June.
This will complete all piling works associated with the new bridge.
Pier 2 and Pier 1 piles will now be cut down to the design level, while the concrete pour for Abutment B is scheduled for the week commencing 22 June.
Steelwork for the pile caps for each pier is also currently in progress.
The existing bridge piers that have been used to support the temporary pile guide frames are scheduled to be demolished in mid-July.
Piling works are continuing on foundations for the new Violet Street Bridge, with Pier 1 completed on 17 June. Abutment A is scheduled to be completed by 26 June.
This will complete all piling works associated with the new bridge.
Pier 2 and Pier 1 piles will now be cut down to the design level, while the concrete pour for Abutment B is scheduled for the week commencing 22 June.
Steelwork for the pile caps for each pier is also currently in progress.
The existing bridge piers that have been used to support the temporary pile guide frames are scheduled to be demolished in mid-July.
-
Violet Street Bridge update
Share Violet Street Bridge update on Facebook Share Violet Street Bridge update on X (formerly Twitter) Share Violet Street Bridge update on Linkedin Email Violet Street Bridge update linkPiling works are continuing on foundations for the new Violet Street bridge.Driving of Pier 1 piles are continuing this week (1 June 2026). This will be followed by Abutment A piling works.Abutment B, Pier 3 and Pier 2 piles are in place.Construction of Abutment B is also in progress.Piling works are continuing on foundations for the new Violet Street bridge.Driving of Pier 1 piles are continuing this week (1 June 2026). This will be followed by Abutment A piling works.Abutment B, Pier 3 and Pier 2 piles are in place.Construction of Abutment B is also in progress. -
Piling works in progress
Share Piling works in progress on Facebook Share Piling works in progress on X (formerly Twitter) Share Piling works in progress on Linkedin Email Piling works in progress linkWorks are moving ahead on the Violet Street Bridge project with piling in progress.
This stage includes the installation of temporary supports on existing bridge piers to assist with the piling works.
The bridge piers will be demolished once piling for the new bridge is completed.
Councillors took the opportunity to visit the site on 15 April, viewing progress of the project firsthand.
Works are moving ahead on the Violet Street Bridge project with piling in progress.
This stage includes the installation of temporary supports on existing bridge piers to assist with the piling works.
The bridge piers will be demolished once piling for the new bridge is completed.
Councillors took the opportunity to visit the site on 15 April, viewing progress of the project firsthand.
-
Demolition works continue on Violet Street Bridge replacement
Share Demolition works continue on Violet Street Bridge replacement on Facebook Share Demolition works continue on Violet Street Bridge replacement on X (formerly Twitter) Share Demolition works continue on Violet Street Bridge replacement on Linkedin Email Demolition works continue on Violet Street Bridge replacement linkWorks to remove the old Violet Street Bridge are continuing as part of its replacement with a stronger, wider and more accessible bridge.
The old bridge deck has been removed with the next phase moving onto piling works for the new bridge foundations. This will include the installation of temporary supports on the existing bridge piers to assist with these piling works.
Once piling has been completed, demolition of the old bridge piers will be undertaken.
A detour route is in place along Selina Street, Newell Highway and Tibbereena Street. This detour will remain in place throughout the duration of the works.
Works to remove the old Violet Street Bridge are continuing as part of its replacement with a stronger, wider and more accessible bridge.
The old bridge deck has been removed with the next phase moving onto piling works for the new bridge foundations. This will include the installation of temporary supports on the existing bridge piers to assist with these piling works.
Once piling has been completed, demolition of the old bridge piers will be undertaken.
A detour route is in place along Selina Street, Newell Highway and Tibbereena Street. This detour will remain in place throughout the duration of the works.
-
Works to start on Violet Street Bridge replacement
Share Works to start on Violet Street Bridge replacement on Facebook Share Works to start on Violet Street Bridge replacement on X (formerly Twitter) Share Works to start on Violet Street Bridge replacement on Linkedin Email Works to start on Violet Street Bridge replacement linkThe Violet Street Bridge replacement is set to take a significant step forward with works to get underway on the project next week.
The project’s work site will be established from today (12 January), with the bridge to be closed from 19 January – prior to the start of demolition works from Wednesday, 21 January.
A detour will be in place along Selina Street, Newell Highway and Tibbereena Street for the duration of the works, which are scheduled to be completed by the end of September 2026 (depending on weather and other factors that may affect the timeline).
The bridge replacement is being undertaken by Saunders Civilbuild Pty Ltd, which was awarded the contract at November’s Extraordinary Council Meeting. Saunders Civilbuild has delivered a number of bridges within the region, including in Narrabri Shire.
The Violet Street Bridge replacement is set to take a significant step forward with works to get underway on the project next week.
The project’s work site will be established from today (12 January), with the bridge to be closed from 19 January – prior to the start of demolition works from Wednesday, 21 January.
A detour will be in place along Selina Street, Newell Highway and Tibbereena Street for the duration of the works, which are scheduled to be completed by the end of September 2026 (depending on weather and other factors that may affect the timeline).
The bridge replacement is being undertaken by Saunders Civilbuild Pty Ltd, which was awarded the contract at November’s Extraordinary Council Meeting. Saunders Civilbuild has delivered a number of bridges within the region, including in Narrabri Shire.
-
Tender awarded for Violet Street Bridge replacement
Share Tender awarded for Violet Street Bridge replacement on Facebook Share Tender awarded for Violet Street Bridge replacement on X (formerly Twitter) Share Tender awarded for Violet Street Bridge replacement on Linkedin Email Tender awarded for Violet Street Bridge replacement linkThe tender for the Violet Street Bridge replacement project has been awarded at yesterday’s Extraordinary Council Meeting.
The tender for the contract was awarded to Saunders Civilbuild Pty Ltd.
The company has strong bridge building experience, having delivered a number of bridges within the region and Narrabri Shire during the past several years.
The Violet Street Bridge replacement project will see the removal of the existing bridge and replaced with a concrete and steel reinforced structure as well as upgraded road approaches.
Overhead lighting near the bridge will be removed starting Tuesday, 11 November. All bridge construction planning and preparation works will be completed by Christmas, ready for demolition of the existing bridge to commence in early January 2026.
Construction of the new Violet Street Bridge is anticipated to be completed by the end of September 2026, depending on weather and other factors that may affect the timeline. A detour will be in place throughout the duration of the works.
The tender for the Violet Street Bridge replacement project has been awarded at yesterday’s Extraordinary Council Meeting.
The tender for the contract was awarded to Saunders Civilbuild Pty Ltd.
The company has strong bridge building experience, having delivered a number of bridges within the region and Narrabri Shire during the past several years.
The Violet Street Bridge replacement project will see the removal of the existing bridge and replaced with a concrete and steel reinforced structure as well as upgraded road approaches.
Overhead lighting near the bridge will be removed starting Tuesday, 11 November. All bridge construction planning and preparation works will be completed by Christmas, ready for demolition of the existing bridge to commence in early January 2026.
Construction of the new Violet Street Bridge is anticipated to be completed by the end of September 2026, depending on weather and other factors that may affect the timeline. A detour will be in place throughout the duration of the works.
-
Tender advertised for Violet Street Bridge replacement
Share Tender advertised for Violet Street Bridge replacement on Facebook Share Tender advertised for Violet Street Bridge replacement on X (formerly Twitter) Share Tender advertised for Violet Street Bridge replacement on Linkedin Email Tender advertised for Violet Street Bridge replacement linkThe tender is now out for construction of the new Violet Street Bridge over Narrabri Creek. The tender advertisement follows completion of the project’s detailed design.
Tenders for the project will close at 11.00am Tuesday, 14 October 2025.
Following evaluation of tenders, a report will be presented at an Extraordinary Council Meeting for Councillors’ consideration to award the contract.
The tender advertisement for the Violet Street Bridge replacement project can be found on Council’s website.
The tender is now out for construction of the new Violet Street Bridge over Narrabri Creek. The tender advertisement follows completion of the project’s detailed design.
Tenders for the project will close at 11.00am Tuesday, 14 October 2025.
Following evaluation of tenders, a report will be presented at an Extraordinary Council Meeting for Councillors’ consideration to award the contract.
The tender advertisement for the Violet Street Bridge replacement project can be found on Council’s website.
-
Violet Street Bridge replacement moves forward
Share Violet Street Bridge replacement moves forward on Facebook Share Violet Street Bridge replacement moves forward on X (formerly Twitter) Share Violet Street Bridge replacement moves forward on Linkedin Email Violet Street Bridge replacement moves forward linkMedia release - 2 September 2025
Preparations are underway for the construction of the new Violet Street Bridge over Narrabri Creek.
The project will see the removal of the existing bridge and replaced with a concrete and steel reinforced structure as well as upgraded road approaches.
The new bridge will feature unrestricted load capacity, dual traffic lanes, shared pathways along both sides and new overhead street lighting.
The $7 million project has been made possible with the contribution of $5 million through the Infrastructure Betterment Program jointly funded by the Australian and NSW Governments under the Disaster Recovery Funding Arrangements.
Tender documentation was currently being prepared, with the project’s tender expected to be advertised this month. A report is proposed to be presented at the October Ordinary Council Meeting for Councillors’ consideration to award the contract.
Upon successful award of the contract and subject to the contractor’s program, site works will commence from mid to late November, beginning with demolition of the existing bridge.
Construction of the new bridge is anticipated to be completed by the end of September 2026, depending on weather and other factors that may affect the timeline. A detour will be in place throughout the duration of the works.
Narrabri Shire Council Mayor Darrell Tiemens said the resulting Violet Street Bridge will be a safer, wider bridge that will cater for all vehicles as well as pedestrians and cyclists.
“While the current Violet Street Bridge is load limited, its replacement will be built to current bridge standards allowing unrestricted heavy vehicle access.
“Further, each side of the bridge will feature a shared pathway for pedestrians and cyclists, which will connect to our existing shared pathway network.”
The new structure will also decrease the time required to remove barriers during flood events. This means the bridge will not need to close as early as per previous flood events – reducing disruption for residents and road users.
Media release - 2 September 2025
Preparations are underway for the construction of the new Violet Street Bridge over Narrabri Creek.
The project will see the removal of the existing bridge and replaced with a concrete and steel reinforced structure as well as upgraded road approaches.
The new bridge will feature unrestricted load capacity, dual traffic lanes, shared pathways along both sides and new overhead street lighting.
The $7 million project has been made possible with the contribution of $5 million through the Infrastructure Betterment Program jointly funded by the Australian and NSW Governments under the Disaster Recovery Funding Arrangements.
Tender documentation was currently being prepared, with the project’s tender expected to be advertised this month. A report is proposed to be presented at the October Ordinary Council Meeting for Councillors’ consideration to award the contract.
Upon successful award of the contract and subject to the contractor’s program, site works will commence from mid to late November, beginning with demolition of the existing bridge.
Construction of the new bridge is anticipated to be completed by the end of September 2026, depending on weather and other factors that may affect the timeline. A detour will be in place throughout the duration of the works.
Narrabri Shire Council Mayor Darrell Tiemens said the resulting Violet Street Bridge will be a safer, wider bridge that will cater for all vehicles as well as pedestrians and cyclists.
“While the current Violet Street Bridge is load limited, its replacement will be built to current bridge standards allowing unrestricted heavy vehicle access.
“Further, each side of the bridge will feature a shared pathway for pedestrians and cyclists, which will connect to our existing shared pathway network.”
The new structure will also decrease the time required to remove barriers during flood events. This means the bridge will not need to close as early as per previous flood events – reducing disruption for residents and road users.
-
September 2025
-
15 September → 14 October 2025
-
05 November 2025
-
November → December 2025
-
January → November 2026
- Why is a new bridge needed?
- What are the features of the new Violet Street bridge?
- Why was this particular design chosen and not a high-level bridge?
- Will there be a detour in place?
- What impact will the works have on local community members and businesses?
- What is the cost of the new bridge and how will this cost be funded?
- Who can I contact for more information about the project or if I have any questions?
-
Click here to play video Violet Street Bridge works - prior to deck removal. Violet Street Bridge works - prior to deck removal.
-
Click here to play video Brekkie on the Bridge event - 20 January 2026 Thank you to everyone who showed interest in our Brekkie on the Bridge event! We were thrilled with the level of community interest, with more than 100 people registering to take part. Unfortunately, we weren’t able to accommodate everyone — though we truly wish we could have. Thank you to those who joined us, and to Saunders Civilbuild for taking part and supporting the event. This was more than a farewell to a piece of Narrabri’s history; it was an opportunity to connect with our community, share the story of the bridge and provide insight into what lies ahead for this important project. We appreciate the community’s ongoing interest and support as we move forward with the next chapter.